From Order to Delivery: The Timeline for an Expandable Container Home

Buyers ask one question more than any other: how long will it take? The honest answer is that the calendar is driven by your own decisions as much as by our factory. Here is the full sequence from order to delivery, and the four things that push projects out.

Every serious buyer asks the same question early in the conversation: how long from order to delivery? It is the right question, because for a holiday park operator or a development, the arrival date decides when revenue starts. But the useful answer is not a single number — it is the sequence of stages, what has to happen in each one, and which parts of the schedule are yours rather than ours.

That distinction matters more than most buyers expect. A factory can hold a production slot, but it cannot lock a layout that the buyer has not confirmed, and it cannot deliver to a site that is not ready. So instead of quoting weeks that would be misleading, this article sets out the real order-to-delivery timeline we work through with Australian and New Zealand customers — with the decision points, the drawing approvals and the delay risks placed where they actually occur.

The seven stages, in order

A double-wing expandable home moves through a predictable sequence. Each stage depends on the one before it, which is why a slow start cannot be recovered later by working faster — the compressed time is always at the end, not the beginning.

The table below is the framework we use in planning conversations. Durations are deliberately not listed, because they depend on your configuration, your quantity and the current production schedule — those are confirmed per order when we quote. What is fixed is the order of operations.

StageWhat happensWhat you need ready
1. Inquiry and scopeYou send target quantity, intended use, destination port and site location; we respond with layout options, freight format and an indicative quotation against that scopeA clear idea of who will use the units and where they are going
2. Specification lockFormat and length, roof type, panel build-up, fittings and internal layout are confirmed. Reference floor plans for 20ft, 30ft and 40ft are matched to the layout your market needsDecision on specification — this is the point where the build is defined
3. Production slotYour order enters the build schedule. Annual capacity runs 800 to 1,000 sets, so the slot you receive depends on how full the line is when you bookA confirmed order, and any deposit terms your contract requires
4. Build and in-workshop QCFrame welding and dimensional checks, panel assembly, plumbing pressure testing, electrical inspection under power, and a full interior and exterior QC sign-off before the unit is packedNothing — but this is where late specification changes are most expensive
5. Packing planThe folded load, handling method, crane reach if required and your on-site opening sequence are documented for your destination and site accessSite access details and the position each unit will occupy
6. Sea freightThe home travels as its own compact load, handled by its eight container corners, protected by the factory-sealed fold positions and the frame's paint systemA freight booking and a destination port — arranged by you, or through a forwarder we coordinate with
7. Delivery and openingThe load is placed on your prepared foundation, the wings open into the full-width floor plate, and your trades connect the marked service pointsA level, stable pad and trades booked for connections

The stages that depend on you, not us

Four of those seven stages are driven by decisions on your side, and this is the part buyers consistently underestimate. Stage two cannot finish until you have chosen the specification — and because layouts are customised per market and confirmed before production, an unconfirmed layout simply holds the order. Stage three depends on when you book relative to the current line, which is why operators planning a multi-unit site often lock the first stage early and add later stages as bookings grow.

Stages six and seven depend on your destination and your site. The freight booking is yours to arrange or to place with a forwarder, and delivery day depends on ground conditions and trade availability. The practical lesson: treat the drawing confirmation and the site preparation as your critical path, because they are the two things a factory cannot move forward on your behalf.

If this is your first import, our site preparation guide covers the foundation, access route and utility marking in detail — working through it while production runs is the single most effective way to keep the overall timeline tight.

The four delays that cost the most time

Across the projects we see, late delivery is almost never the factory being slow. It is one of four things, and every one of them is avoidable at the planning stage.

The first is changing the specification after production starts. Once a frame is welded and panels are cut, a change to layout or configuration is not an edit — it is rework, and rework has to find space in a schedule that is already committed to other orders. Lock the specification before stage four and this risk disappears entirely.

The second is an unready site. A folded home only opens square onto a square foundation, and a load cannot be placed if the pad is not level or the access route will not take the vehicle. Site works that slip a week do not delay the factory — they delay your opening, because the unit is finished and waiting.

The third is incomplete destination information. Packing plans are built around a specific port and a specific site access, so vague details produce assumptions — and assumptions about crane reach or unloading position are exactly where an otherwise smooth project stalls on arrival.

The fourth is booking the production slot late. With 800 to 1,000 sets of capacity a year split across formats, a crowded period is a real thing. Ordering early costs nothing; needing a slot in a specific week at short notice is when schedules become difficult.

How to keep the calendar under control

Three habits make the biggest difference. Confirm the specification and the layout drawings as early as you can, and then treat that version as final for production. Finish site readiness during the production window rather than after the shipping advice arrives, so delivery day is the end of the project rather than the start of site works.

And give the destination details early — port, address, access, and the position each unit will occupy. Those details feed directly into the packing plan, which is the document that makes the final stage predictable. Everything else on the timeline, from the welded frame to the sealed fold positions, is already handled inside the product.

Frequently asked questions

How long does it take from order to delivery?

It depends on your configuration, quantity and where your order falls in the current production schedule, so we confirm the timeline per order rather than quoting a fixed number. What is predictable is the sequence: specification lock, production slot, build and QC, packing plan, sea freight, then delivery and opening.

Can the timeline be shortened?

The most effective way is to lock your specification and confirm the layout drawings early, and to have the site ready before the unit ships. Those two stages are on your side; once production begins, the build and QC sequence cannot be compressed without compromising the inspections each unit goes through.

What happens if I need to change my layout after ordering?

Changes before production starts are straightforward, because layouts are confirmed before the build begins. Changes after welding and panel cutting are rework rather than edits, and they have to be scheduled into committed production time — which is why we ask for the specification to be final before stage four.

When should I start site preparation?

During the production window, not after shipping. Foundations, access and utility markings need to be complete before the unit arrives, because the load is placed and the wings open on delivery day. Our site preparation guide sets out the stages; your trades can work through them while the home is being built.