2026-10-13 · 8 min read

Who Does What? Factory Scope, Delivery Scope and Site Scope for Container Homes

Most container home projects do not fail on price or on product. They fail on an unowned step — a drawing nobody requested, a trade nobody booked, a pad that was never levelled. This is the responsibility map we hand buyers at order stage, so the boundaries are agreed before the ship sails.

Every imported building arrives at the same moment: a factory-complete unit on a truck at a prepared site, and a project team that has never worked on this product type before. The unit itself is the easy part. What determines whether the placement is a one-day event or a three-week problem is entirely a matter of who owns which step, and whether that ownership was agreed in writing before the order was placed.

This guide maps the scope in three bands. The factory scope is what leaves our building — the structure, the finish, the documentation. The delivery scope is what happens between our gate and your pad. The site scope is everything that happens after the unit is lifted off the transport. Within each band we have set out what we supply, what is normally arranged locally, and where the handover points sit.

The handover points are the important part. In our experience the six items listed at the end of this guide account for the overwhelming majority of placement delays, and every one of them is unowned at the point where the order is confirmed.

Band one: the factory scope

This is what the order covers. It is fully documented at order confirmation and it is the part of the project with the fewest surprises, because it happens under our own quality control before the unit ever leaves.

Factory scope itemWhat we supplyNotes
StructureWelded galvanized square tube frame with eight shipping container corners on the expandable lineThe corners are what makes the unit liftable and stackable using standard container handling
Wall and floor build-up18mm cement board floor (asbestos-free) with PVC or SPC flooring; 0.4mm double-sided purification wall panels; 25mm metal carved exterior claddingSpecification is a confirmed decision at order stage, not an option chosen later
Roof and waterproofingButyl tape sealing at fold positions as standard; membrane or FRP available; gable (2.3m internal) or flat roof (2.4m internal)Flat roof was developed for Australian clearance requirements — for that market it is a requirement, not a preference
Openings and services layoutFactory-fitted black-frame windows; AU-standard window and door options; Australia-certified plumbing availableService positions are fixed in the factory and drive the water and electrical drawings
Open or folded mechanismFolding mechanism factory assembled, with roof folds sealed at the factory so the unit can fold and reopen without secondary waterproofingThe seal is what makes repeat cycles practical rather than a maintenance project
DocumentationInstallation instructions, electrical layout, water supply and drainage drawings, reference floor plans, packing planThese are the documents a licensed tradesperson or building practitioner needs on site — see the downloads section
QC and packingFactory QC before dispatch; sea-freight packing documented per orderThe packing plan travels with the order and governs lifting, load and sequence

Band two: delivery scope

Between our gate and your pad there are four handoffs, and each one is where an imported building quietly loses a week if it is not planned.

  • Export packing and loading: handled at origin under the packing plan. This is ours.
  • Sea freight and discharge: arranged by the buyer or their forwarder, or by us on request. The contract, the insurance and the destination port are the buyer decision.
  • Customs clearance: the importer of record. Documentation must match the packing list and commercial invoice exactly.
  • Onward transport from port to site: needs a vehicle and route that suit the unit's transport dimensions, plus crane access at the pad.

The forwarder and clearance steps are routine but unforgiving, and the most common failure is a mismatch between the packing list, the commercial invoice and the physical unit. Clear these before loading, not after arrival at port. The how-shipped guide covers the full journey from our factory floor through to placement.

Band three: the site scope

This is where most of the cost and most of the schedule live, and it is almost never included in a factory quotation. For Australian and New Zealand sites it includes five distinct workstreams.

Site scope workstreamWhat is involvedWho normally does it
Pad and foundationLevel, stable supports sized to the opened footprint; blocks, piles or slab depending on ground conditions; drainage away from the supportsLocal earthworks contractor; the foundation guide covers the choice
Crane and placementLifting the folded unit off the transport through the eight container corners and setting it on the supportsLocal crane hire, coordinated with the transport window
Opening and securingOpening the wings or folding structure on site, sealing checks at fold positions, leveling and securingOur installation instructions govern it; local labour carries it out
Service connectionsWater, power and drainage terminated at the documented connection points and completed by licensed tradesLicensed local trades — not the factory, and not removable from the equation
Compliance and supervisionAny building approval, planning approval, engineering assessment or certified building practitioner supervision required by the local authorityLocal council, building certifier or licensed practitioner, engaged by the buyer before delivery

One point deserves emphasis: service connections are licensed-trade work at both ends, and they are not optional and not substitutable. A unit can arrive, be placed and be perfectly sound, and still be unusable until a licensed plumber and electrician have completed the connections to the documented points. The services guide covers those connection points in detail.

The six handover points where projects stall

In order, these are the steps that most often have no named owner at order confirmation.

  • Pad specification: who designs the foundation for this exact unit, and who certifies the level tolerance the transport and the placement depend on.
  • Crane booking: crane capacity, reach and the transport access route, booked before the vessel arrives rather than after the unit lands.
  • Local trades: which plumber, electrician and drainage installer are contracted, and for which date.
  • Compliance: whether the site needs a building approval, a planning approval or practitioner supervision, and who has already had that conversation with the council.
  • Documentation handover: who receives the installation instructions and service drawings, and confirms they match what the trades expect on arrival.
  • Acceptance: who inspects the unit on arrival, against what checklist, and before what point in the payment schedule.

None of these is difficult. All of them are invisible until they are late. A project that names an owner for each of the six before the order is placed is a project that places in days rather than weeks.

How to write this into your order

Three things make the boundaries stick. First, state the site scope in writing at order stage, including what you are doing yourself — a supplier who knows your pad is already levelled will quote differently and more accurately. Second, send the documentation pack to your trades and your practitioner before dispatch, not on arrival; the installation instructions only help if they arrive before the people who will read them are booked. Third, define the acceptance point and the checklist that goes with it, so inspection is a scheduled event rather than an argument.

If you send us the site location, the delivery window and who is handling the pad, the crane and the trades, we reply with the packing plan, the reference floor plans, the installation and service drawings and an indicative quotation with the scope boundary stated explicitly. That is the same conversation, done early, that prevents the six problems above.

Frequently asked questions

Does the factory price include installation and site works?

No. Foundation or pad, crane and placement, licensed trade connections and any council or approval fees are site-side costs and sit outside the unit price. A quotation that appears to include them is making an assumption about your site. Ask for the site-exclusion list in writing — it is usually the most revealing part of any quote.

Can we install the unit ourselves to save on labour?

The unit is placed using the eight container corners and standard container handling, and the folding mechanism is factory assembled, so placement does not require specialist equipment beyond a crane. Service connections, however, are licensed trade work at both ends and cannot be self-performed. Those two steps should not be confused — one is a lifting operation, the other is regulated work.

Who arranges customs clearance?

The importer of record, which is normally the buyer or their forwarder. The practical requirement is that the packing list, commercial invoice and the physical unit match exactly. This is the most common cause of delay on imported buildings and it is resolved before loading, not after the unit reaches port.

Do we need local approval before the unit ships?

Often yes, and it should be settled before the order is placed. Australian sites may need planning approval, building approval or practitioner supervision depending on state, council, zone and overlays; New Zealand has its own pathways, including the 70m2 small standalone dwelling exemption with its conditions. Neither country treats origin as relevant — what is assessed is the design and the site.

What documentation should we request before ordering?

Installation instructions, the electrical layout, the water supply and drainage diagram, reference floor plans and the packing plan. Every one of these is in the downloads section or travels with the order. Their purpose is specific: they are what your licensed trades and your building practitioner need in order to work from a real document rather than a verbal handover.