2026-10-25 · 11 min read
Piles or Blocks on Soft Ground for an Expandable Container Home
On soft ground a container home is not a product decision, it is a site classification decision. Classify the ground first, then the foundation system chooses itself — and the folding mechanism makes the levelness tolerance stricter than any builder assumes.
On soft ground, a container home is a site classification decision before it is a product decision. The format is usually chosen already, and the real question is whether the ground will hold it level, and hold it the same way at every corner. Get that wrong and the failure does not look like a foundation failure. It looks like a door that will not close, a wing that opens out of square, and a floor that humps where the ground was weakest.
So the sequence matters, and it is not the one most buyers assume. You do not choose a foundation first and look for a ground to match it. You classify the ground, you test whether that classification lands in the problem category, you match one of three systems to it, and a local engineer certifies the design against the code that applies there.
Step one: what class of ground is it?
In Australia the site class is not a judgement call, it is a defined classification with a defined consequence. The ABCB Housing Provisions 2022 require that the foundation where the footing is to be located must be classified in accordance with AS 2870, and the standard works out how much the ground is expected to move as its moisture content changes across the seasons. The classification decides which design route is open to you.
Two of the classes behave differently, and both matter here. Class M and above carry a further split for deep-seated movement, where the depth of expected moisture change reaches 3 m or more. Where that split results in a class of M-D, the design of footings and slabs falls outside the scope of the ABCB Housing Provisions and must be referred to AS 2870.
| Site class | Ground description under AS 2870 | Characteristic surface movement | Design route under NCC 2022 |
|---|---|---|---|
| A | Most sand and rock sites with little or no ground movement from moisture changes | Negligible | Section 4 of the ABCB Housing Provisions available |
| S | Slightly reactive clay sites, which may experience only slight ground movement from moisture changes | 0 to 20 mm | Section 4 of the ABCB Housing Provisions available |
| M | Moderately reactive clay or silt sites, which may experience moderate ground movement from moisture changes | 20 to 40 mm | Section 4 of the ABCB Housing Provisions available |
| H1 and H2 | Highly reactive clay sites, further divided by the depth of the expected movement | 40 to 60 mm (H1); 60 to 75 mm (H2) | Must refer to AS 2870 for design and construction information |
| E | Extremely reactive sites which may experience extreme ground movement from moisture changes | Greater than 75 mm | Must refer to AS 2870 for design and construction information |
| P | Sites which include soft soils such as soft clay, silt or loose sands; landslip; mine subsidence; collapsing soils; soils subject to erosion; reactive sites subject to abnormal moisture conditions, or sites which cannot be classified otherwise | Not applicable | Must refer to AS 2870 for design and construction information |
What actually pushes a site into Class P
Class P is the category that changes the project, and it is worth reading the triggers rather than just the label. Council lot classification reports in New South Wales list the conditions that produce it: bearing capacity below 100 kPa for strip and pad footings, below 50 kPa for beams and slab panels and slab support thickenings, the presence of fill whether controlled or uncontrolled, and ground that keeps moving for reasons other than normal seasonal moisture change.
Fill deserves attention because it is the most common soft-ground trigger in practice, and the treatment depends on how it was placed. Fill placed and tested to the earthworks standard AS 3798 is controlled fill, and controlled fill no deeper than 0.4 m, or 0.8 m in sand, leaves the site classified as the natural ground was before. Uncontrolled fill gets no such latitude, and where it is shallow the only way out is to take every footing through it to natural soil. Control means tested, not merely compacted.
The other trigger that catches buyers out is not geological at all. Abnormal moisture conditions arise from trees on or beside the site, a building recently removed, poor drainage, a plumbing leak, or a neglected garden watering regime, and AS 2870 treats these as a legitimate reason to classify a site as P.
| Trigger | What it means on your site | Where the rule sits |
|---|---|---|
| Bearing capacity below 100 kPa | The ground cannot carry a strip or pad footing spread across normal dimensions | AS 2870 site classification, reported in council lot classification reports |
| Bearing capacity below 50 kPa | Beams, slab panels and slab thickenings need more than the ground can give | AS 2870 site classification |
| Uncontrolled fill | No testing record for the fill, so the site is classified P and footings must reach natural soil | AS 2870 clause 2.5.3 |
| Controlled fill within limits | Fill placed and tested to AS 3798, no deeper than 0.4 m, or 0.8 m in sand, keeps the original site class | AS 2870 clause 2.5.3 |
| Soft clay, silt or loose sand | Compressible ground that keeps settling under load rather than stopping at a stable level | AS 2870 Class P definition |
| Abnormal moisture conditions | Trees, a removed building, poor drainage or a leak change the moisture state under the footing | AS 2870 clause 1.3.3 |
| Landslip, mine subsidence, collapsing or eroding soils | The ground is moving, or is expected to move, for reasons a foundation cannot simply outlast | AS 2870 Class P definition |
Piles, blocks or slab on soft ground
Three foundation systems cover almost every container home installation, and on soft ground they separate cleanly by how they transfer load. A pile takes the load past the soft zone to a founding layer underneath it. A block spreads it across prepared ground right below grade. A slab spreads it across a continuous platform. Which one works is decided by the ground, not by preference or by price.
The container format adds one condition a conventional building does not have, and it changes the tolerance everybody else argues about. The folded unit travels and lands on its own frame, and when the wings open that same frame becomes the floor plate of a full-width home. If one corner settles further than another, the structure twists, and a twisted structure does not open square. The base has to be level to a tolerance set by the folding mechanism and the panel fit, not the looser number a builder would quote.
| Foundation system | How it transfers load | Where it holds its advantage on soft ground | Where it needs engineering attention |
|---|---|---|---|
| Piles | Each pile carries its share of the frame down to a founding layer below the soft zone, keeping the structure above grade | Soft or filled ground, sloping sites and high water tables, where a slab would have to be dug through deep fill | Depth, spacing and capacity are set by the geotechnical and structural engineer; no prescriptive design applies once a site is classified P |
| Foundation blocks and bearers | Load spread through discrete blocks set on prepared ground beneath the frame carrying points | Level sites with sound bearing, where a shallow system is sufficient and a full slab is unnecessary | The blocks sit at grade, so differential settlement across the base shows up directly as the frame twisting; levelling tolerance is governed by the folding mechanism |
| Concrete slab or pad on ground | A continuous platform under the opened footprint, usually stiffened at the edges | Permanent installations and wet sites where keeping the floor line clear of the ground matters | Requires excavation to a sound founding layer; over uncontrolled fill it must either be taken through the fill or designed for its movement, and the second option is the expensive one |
The Australian compliance path
The National Construction Code sets out what a compliant foundation looks like, and the path is shorter than most buyers expect until the site class turns out to be H, E or P. Performance Requirement H1P1 is satisfied by designing and constructing footings and slabs to AS 2870, to AS 3600, or to Section 4 of the ABCB Housing Provisions where that section limits are met. Section 4 is the free prescriptive route, and its limits are specific enough to quote.
New South Wales adds a variation that is easy to miss: the NSW variation to H1D4 requires a damp-proofing membrane for the purposes of Clause 5.3.3.1 of AS 2870. The excavation and fill rules are equally concrete. Footing excavations must be clean cut with vertical sides wherever possible, the base free of loose earth, tree roots, mud and debris, topsoil with grass roots removed, and fill under a slab controlled or rolled. For piles the reference is AS 2159, which sets out minimum requirements for the design, construction and testing of piled footings on land and immediate inshore locations, and AS 2870 Appendix G covers deep footings such as driven piles, bored piers and steel screw piles.
One point deserves attention from buyers who assumed otherwise. AS 2870 gives no advice on detailing the connection of the superstructure to the footing for wind or earthquake actions, so the anchorage between a container corner casting and its support is a separate design task, referencing AS 1170.4 for earthquake actions and AS/NZS 1170.2 for wind.
| Step | What the code requires | Official source |
|---|---|---|
| Classify the ground | The foundation where the footing is to be located must be classified in accordance with AS 2870 | ABCB Housing Provisions 2022, Part 4.2.2 |
| Pick a compliance route | Footings and slabs satisfy H1P1 by following AS 2870, AS 3600, or Section 4 of the ABCB Housing Provisions | NCC 2022 Volume Two, H1D4(1) |
| Know when Section 4 closes | Section 4 may only be used where the footing is on a Class A, S or M site with uniform bearing capacity, the slab is not more than 18 m long or wide, the site is normal, and the structure has no more than two trafficable floors | NCC 2022 Volume Two, H1D4(2) |
| H, E and P sites | Where a site is classified H, E or P, reference must be made to AS 2870 for design and construction information | ABCB Housing Provisions 2022, Part 4.2.2 |
| Excavation and fill | Excavations must be clean cut with vertical sides, free of loose earth, tree roots, mud and debris, with grass-rooted topsoil removed; fill under a slab must be controlled or rolled fill | ABCB Housing Provisions 2022, Part 4.2.3 and 4.2.4 |
| NSW variation | A damp-proofing membrane is required for the purposes of Clause 5.3.3.1 of AS 2870 | NCC 2022 Volume Two, H1D4 NSW variation |
| Piles | Minimum requirements for the design, construction and testing of piled footings for civil engineering and building structures on land and immediate inshore locations | Standards Australia, AS 2159-2009 |
| Anchorage, not just bearing | AS 2870 gives no advice on detailing the connection of superstructures to the footing systems for wind or earthquake loads | AS 2870-2011 scope note; AS 1170.4 and AS/NZS 1170.2 |
New Zealand: good ground, and the liquefaction change
Across the Tasman the logic is the same but the vocabulary differs. New Zealand building consent is assessed against the New Zealand Building Code, and the foundation question is settled by whether the ground qualifies as good ground. Ministry of Building and Housing guidance is explicit: if ground bearing testing or a soil report shows the ground does not meet the bearing capacity required for good ground, further investigation by a geotechnical or soil engineer should be completed. A geotechnical report is a specific document with specific contents. It records the ultimate bearing capacity on each lot, the presence of expansive clay, a preliminary liquefaction assessment, topsoil depths, uncertified fill requiring specific site investigation, and slope stability problems that may limit any building platform. Where the ground is not good ground, the foundations are subject to specific engineering design and further investigation or improvement, and NZS 3604 for timber framed buildings is not a substitute.
The change buyers most often have not heard about is the liquefaction rule. In November 2019, Acceptable Solution B1/AS1 was amended so that it could no longer be used on liquefaction-prone ground, and from 29 November 2021 those rules became mandatory nationwide rather than only in Canterbury. Where the ground is liquefaction-prone, robust foundations and a liquefaction assessment are required, and the assessment determines whether specific engineering design foundations are needed. Councils also run a two-report sequence: a Geotechnical Assessment Report for consent and a Geotechnical Completion Report after earthworks, with a producer statement covering the building platform, excavations, sub-soil drainage and compacted fill. A resource consent may also be needed, because earthworks and building on hazard-prone land are land use activities under the Resource Management Act.
Why 3.8 tonnes still needs a designed foundation
A light structure needs less engineering than a house, and on sound ground that holds. The standard 20ft double-wing unit weighs about 3.8 tonnes folded, heavier than the roughly 2.6 tonnes common in the industry because the steel in the frame and floor is real, and the load reaches the ground through eight galvanized container corner castings at known points.
Soft ground changes that in three ways, and none of them are about tonnage. The load path has to bypass the soft zone, which is a piling problem rather than a bearing problem. Differential settlement becomes the governing issue, because a twisted frame cannot open square. And the code horizon is 50 years: AS 2870 classifies the movement expected over that period, not over the first wet season. Ground acceptable for a short-term camp is a different question from ground acceptable for a home someone keeps.
The soft ground order checklist
Each line below is a document, a number or a decision, and every one of them is cheaper to settle before production than after the unit has been craned onto its supports. None of them is a request for a price quote.
- Site classification under AS 2870, commissioned before the order rather than after the ground works are scheduled.
- The classification result, and if it is P, the specific trigger that produced it: fill, soft soil, trees, moisture conditions, or one of the listed ground hazards.
- Whether the design will be referred to AS 2870 rather than taken from a prescriptive table, which is automatic for H, E and P sites.
- The foundation design basis for the folded weight of the chosen format at its eight container corner points, and for the opened footprint including any veranda.
- The levelness tolerance stated against the folding mechanism and panel fit, rather than against a generic builder rule of thumb.
- A settlement monitoring plan, with a level re-check after the first wet season.
- Surface drainage detail, with ground graded away from the footings and water diverted to a lawful point of discharge.
- Excavation detail: clean cut with vertical sides, topsoil with grass roots removed, base free of loose earth, tree roots, mud and debris.
- The fill position, including whether any fill on site is controlled fill tested to AS 3798 and within the 0.4 m, or 0.8 m in sand, limit.
- Anchorage details for wind and earthquake actions, because the AS 2870 footing designs do not cover the superstructure connection.
- For New Zealand: evidence that the ground is good ground, or a specific engineering design, plus the liquefaction position if the land is liquefaction-prone.
- For New Zealand councils: the Geotechnical Assessment Report for consent, the Geotechnical Completion Report after earthworks, and a producer statement covering the building platform.
Two documents shorten that conversation considerably. The full specification table at /specifications/ lists every verified figure for every format in one comparable place, including folded and opened dimensions, the corner casting arrangement and the frame construction your engineer designs against. The Download centre holds the dimensioned 20ft floor plan with electrical and plumbing layout, the water supply and drainage diagram for the standard bathroom module, and the flat roof electrical plan showing circuit routing, socket positions, lighting and control box placement. Give those to the geotechnical engineer before the design is priced.
What we supply is the side that is ours: the folded weight of the chosen format, the container corner carrying points, the opened footprint for each size, and the roof and veranda configuration that changes that footprint. Everything configuration-specific is confirmed per order, so the drawing your engineer designs from is the drawing that ships. Annual production capacity runs at 800 to 1000 sets, and hundreds of these homes have been delivered to Australian customers over the past two years, so a foundation-led installation programme is a scheduling exercise rather than a one-off. Send the site classification report, the format, the roof type, the veranda decision and the destination, and the reply is specific.
Frequently asked questions
Do I need a geotechnical report before I order a container home in Australia?
On soft or filled ground, yes. The ABCB Housing Provisions 2022 require that the foundation where the footing is to be located must be classified in accordance with AS 2870, and that classification comes out of a geotechnical site investigation. Where the classification is H, E or P, reference must be made to AS 2870 for design and construction information, which means a site-specific engineering design rather than a prescriptive table. The trigger for the investigation is the ground itself: fill without an AS 3798 testing record, soft clay, silt or loose sand, abnormal moisture conditions from trees or a removed building, or any of the listed ground hazards. On Class A or Class S ground the requirement is far lighter.
Can I put an expandable container home on soft ground at all?
Usually yes, but the soft ground decides which system you use rather than whether the home can go there. Piles are the standard answer on soft or filled ground because they carry the load past the soft zone to a founding layer below it and keep the structure above grade. Foundation blocks work on level ground with sound bearing. A slab works where excavation to a sound founding layer is practical. What soft ground rules out is guessing: AS 2870 prescriptive designs do not apply once a site is classified P, and AS 2870 gives no advice at all on detailing the connection of the superstructure to the footing for wind or earthquake actions, so anchorage at the container corner castings is a separate design task.
What is the difference between pile foundations and block foundations for a container home?
The load path. A pile takes the share of the frame it carries down to a founding layer beneath the soft zone, so the ground that matters is the ground below the problem, and the structure stays above grade. A block spreads the load across prepared ground immediately below grade, which is cheaper and simpler on sound level ground but leaves the structure at the mercy of differential settlement across the base. For a folding or expandable unit that distinction is amplified, because a base that settles unevenly twists the frame and the unit will not open square. Piles are designed, constructed and tested under AS 2159, while AS 2870 covers the prescriptive piled footing designs for the site classes where those apply.
Who is responsible for designing the foundation, the container home supplier or my builder?
Your side owns the ground assessment, the local requirements and the ground works design, because bearing, slope, fill and exposure are site facts no factory can see from a distance. Our side owns the data the design needs: the folded weight of the format, the container corner carrying points, the opened footprint for each size, and the effect of roof type and veranda on that footprint, all confirmed per order. The engineering design itself is produced by a locally accredited engineer who can sign it, and that is also who certifies it to the National Construction Code or the Building Act.
Do the same foundation rules apply in New Zealand, including on liquefaction-prone land?
The framework is parallel but the language differs. In New Zealand the ground must qualify as good ground, and Ministry of Building and Housing guidance states that if ground bearing testing or a soil report shows the ground does not meet the required bearing capacity, further investigation by a geotechnical or soil engineer should be completed. Where it does not qualify, foundations are subject to specific engineering design and further investigation or improvement, and NZS 3604 for timber framed buildings is not a substitute. On liquefaction-prone land the position is strict: Acceptable Solution B1/AS1 was amended in November 2019 so that it could no longer be used on liquefaction-prone ground, and those rules became mandatory nationwide from 29 November 2021. Councils also require a Geotechnical Assessment Report for consent and a Geotechnical Completion Report after earthworks, with a producer statement covering the building platform.
Explore these models
- Double-Wing Expandable Container House — Wings fold down for shipping, open up to a full-width home with veranda options.
- Flat Pack Container House — Panelized units that stack efficiently in a shipping container for low freight cost.
- Folding House — Quick-open folding structure for holiday parks, backyards and rapid deployment.
Not sure which format fits your project?
Send your target units, destination port and intended use — we reply with layout options, freight format and an indicative quote.
Start an inquiry